Project Library Ninth Assurance Report

Ampliacion infraestructura portuaria entrada y salida del recinto portuario para vehiculos – salida de transporte pesado, Puero SantoTomas de Castilla

Project Details

Project Number
6
Sector
Transport
Subsector
Water transport
Value (USD)
$2,288,339
Value (Local Currency)
17,711,604 GTQ
Exchange Rate
0.1292
Associated Report

Ninth Assurance Report (2021)