Phase 5: Project Execution

Non-delivery and ghost works

The project is not executed, or is only partially delivered, despite funds being committed or spent.

Red Flags & Indicators

  • Reported outputs and milestones are not supported by site verification, geotagged evidence, and independent checks.
  • Advance payments or disbursements continue despite limited mobilisation, minimal equipment on site, and low physical progress.
  • Schedules are repeatedly re‑baselined and delays reclassified without a credible recovery plan.
  • Handover, defects, and completion documentation is incomplete, yet certificates are issued to trigger payments.
  • Controls for tracking and verifying physical progress are weak or absent.
  • Alignment between physical and financial progress control systems is weak or absent.

Stakeholder Guidance

Stakeholder Exposure

Exposure includes payment freeze; higher risk of contract termination; debarment and enforcement risk; increased risk of disputes and recovery claims; severe cashflow stress; and reputational damage from non-delivery. allegations.

Decision Point

Before submitting payment claims, verify evidence of completion of on-site outputs; implement a documented remediation plan when physical progress is not demonstrated.

Mitigation Actions

• Adopt recognised, verifiable methods to measure physical progress of works
• Verify work completion before claiming payment (site diaries, measurements, photos and geotagged evidence where used, supervisor and engineer sign-offs)
• Do not process payment claims without supporting evidence of completion
• Separate site supervision and progress reporting from invoice preparation and payment certification roles
• Maintain an auditable evidence pack for each milestone and payment claim
• Document corrective actions taken to complete unfinished works (recovery plan, rework, revised milestones)
• Use internal compliance escalation processes and whistleblower channels, where available, to report any pressure to certify ghost works or issue completion certificates without evidence, pausing payments pending investigation and documented resolution

Mitigation Resources

Control work progress, site evidence, delivered quantities, completion records, and records supporting claims through formal evidence requirements, site or measurement records, independent review, and verification before claim submission, internal sign-off, or payment processing.

Change control, delivery verification, and payment integrity — https://toolbox.infrastructuretransparency.org/resource/change-control-delivery-verification-and-payment-integrity/

Assess fraud risks and apply prevention, detection, investigation, and corrective-action controls to work progress, site evidence, delivered quantities, completion records, and records supporting claims, including ghost works, inflated progress claims, or unsupported completion certificates.

Fraud control management — https://toolbox.infrastructuretransparency.org/resource/fraud-control-management/