Phase 3: Planning & Design

Design imprecision (overdesign or incomplete specifications), gold plating, and scope inflation

Scope and design are left incomplete to allow for later adjustments or expanded beyond functional requirements to increase contract value and extract rents, while more cost-effective or phased alternatives are disregarded.

Red Flags & Indicators

  • Design specifications are incomplete or unclear, allowing the scope, quantities, materials, or costs to be changed later without proper control.
  • Capacity, performance, or design standards are higher than needed for expected demand and service requirements, without clear justification.
  • Design revisions add new work or higher-cost features without a clear reason or an updated cost-benefit assessment.
  • Alternative design options are not properly assessed, and lower-cost options are rejected without supporting evidence.
  • Quantities, unit rates, or contingency amounts are higher than comparable benchmarks without explanation, increasing the estimated project cost.
  • Affordability, user charges, or other financial impacts are not updated when the design scope expands or higher-cost features are approved.

Stakeholder Guidance

Stakeholder Exposure

Exposure includes pressure to add premium features beyond need; inflated designs; higher cost and schedule risk and later claims; and reputational risk if intentional design imprecision, scope inflation and 'gold-plated' projects are identified.

Decision Point

Before endorsing or proposing premium scope or design specification or change, request documented rationale and approvals.

Mitigation Actions

• Request documented justification and approvals for design and scope decisions
• Retain evidence, benchmarks, and cost-benefit or alternative/phasing analysis
• Document scope, design and standard assumptions and cost implications for any change
• Require internal approval for material scope/design changes
• Do not submit or accept scope increases without a clear service need and documented decision trail
• Seek independent technical and value-for-money review when scope expands materially beyond demand/service requirements and lower-cost alternatives are dismissed without evidence